    Like most newbies I have been reading the forum for months and have been inspired by the many variations and materials that members are building their routers from.

    I have been building for a couple of months and now have something to show for the effort. Don't ask for drawings as they are in my head and change to suit the materials I have available and the problems I encounter as I construct it. I know this is a cop out but I would rather be making chips than drawing pictures.

    The biggest hurdle was the electronics as I have very little experience other than how to solder. As this was going to be the critical component for me I decided to get the Xylotex board and if I could mount it and get it going the rest should be easier.

    The box I got was not big enough to house the transformer and board so I got another one and put the transformer in one and driver board in the other.

    Once I was confident I had everything working I got the 269 oz motors.

    Here are some photos of the finished driver board and power supply.

    cheers,
    Rod

    Perth, Western Australia

    Similar Threads:
    Attached Thumbnails Attached Thumbnails Gantry Router Log-stepper-drive-internal-jpg   Gantry Router Log-stepper-drive-front-jpg   Gantry Router Log-stepper-drive-rear-jpg  


  2. #2
    Registered
    Join Date
    Oct 2005
    Location
    Australia
    Posts
    612
    Downloads
    0
    Uploads
    0

    Default

    So the electronics, motors and cables have been completed.

    I decided to make the base from steel and the gantry from aluminium. My choice for a steel base is that it adds weight and stability and because it is fixed it does not require additional motor power.

    I also wanted to have the rail supported laterally and vertically along it's lenght. The rail is 2 inch by 1 inch bright mild steel and is attached to the sides of the frame. The backbone and turnbuckles let me adjust one side without affecting the other side. There are slotted holes in the crossmembers to allow for adjustments.

    Rather than waffle on perhaps if I post pictures it will be clear as mud for everyone.

    regards,
    Rod

    Perth, Western Australia.

    Attached Thumbnails Attached Thumbnails Gantry Router Log-base-jpg  
    Last edited by Rodm1954; 12-04-2005 at 10:36 AM.


  3. #3
    Registered
    Join Date
    Oct 2005
    Location
    Australia
    Posts
    612
    Downloads
    0
    Uploads
    0

    Default

    The bearing carrier contacts three faces of the rail and I will be able to get the fourth face of the rail when the lower gantry crossmember is fixed in place.

    The bearing holders are adjustable so that I will be able to plumb the gantry as well as make minor adjustments to each bearing.

    There will be a total of twelve bearings on each side.

    The first photo shows the bearing carrier on the rail. Second is the bearing carriage and the last is one of the bearing mounts before it was painted. Skateboard bearing have been used.

    Well that is about it for the moment. Next I will be making a frame to hold the router and at the same time I will strip down the base and paint.

    Just ask if you want more detailed photos or descriptions.


    cheers,
    Rod

    Perth, Western Australia

    Attached Thumbnails Attached Thumbnails Gantry Router Log-bearing-rail-jpg   Gantry Router Log-bearing-carrier-jpg   Gantry Router Log-bearing-assembly-jpg  
    Last edited by Rodm1954; 12-04-2005 at 08:51 AM.


  4. #4
    Registered Lionclaw's Avatar
    Join Date
    Jan 2005
    Location
    USA
    Posts
    253
    Downloads
    0
    Uploads
    0

    Default

    It's looking great Rod. Your nicely organized and labeled driver box will hopefully encourage me to build one. I currently have my driver board hanging from the wires on my x-axis motor It's only a matter of time before one of those wires comes loose and fries the driver

    Andy
    CNC Kits - http://www.comptonsoft.com/cncweb/


  5. #5
    Member ger21's Avatar
    Join Date
    Mar 2003
    Location
    Shelby Township
    Posts
    35538
    Downloads
    1
    Uploads
    0

    Default

    Are you counting on the stiffness of the gantry to keep the baearings tight to the rails? It seems like the bottom bearings may be able to pull away, but if the entire machine is aluminum and / or steel, it might not be a problem.

    What's the overal size of the machine, and working area? It looks about 4 ft long? If it ends up as heavy as it looks like it might, I think the Xylotex might be a bit underpowered. But if it is, you can always sell it and upgrade later if you need to. It will certainly run the machine, you just might want to upgrade for higher speeds later.

    Looks good, though. Keep us posted.

    Gerry

    UCCNC 2017 Screenset
    [URL]http://www.thecncwoodworker.com/2017.html[/URL]

    Mach3 2010 Screenset
    [URL]http://www.thecncwoodworker.com/2010.html[/URL]

    JointCAM - CNC Dovetails & Box Joints
    [URL]http://www.g-forcecnc.com/jointcam.html[/URL]

    (Note: The opinions expressed in this post are my own and are not necessarily those of CNCzone and its management)


  6. #6
    Registered
    Join Date
    Oct 2005
    Location
    Australia
    Posts
    612
    Downloads
    0
    Uploads
    0

    Default

    Lionclaw
    The labels are for me to remember the details of the unit and where to plug everything in.
    Apart from my poor memory if you live in a remote part of the world it can be very inconvenient and expensive to send bits off for repair.

    Last edited by Rodm1954; 12-04-2005 at 09:53 AM.
    cheers,
    Rod

    Perth, Western Australia


  7. #7
    Registered
    Join Date
    Oct 2005
    Location
    Australia
    Posts
    612
    Downloads
    0
    Uploads
    0

    Default

    Gerry,

    The dimensions are X 28 inches, Y 39 inches and Z ? at this stage. I have probably got X and Y mixed up but these are the base dimensions. Base is steel and gantry will be aluminium.

    As you have pointed out I too have pondered over the lower bearings maintaining contact.

    Tests today seem to work OK with just two ali flats clamped between the bearing carriers. The bearing rails are 1 inch square and the plate they are attached to is 3/8 inch. The sides of the gantry will be 3/8 ali and will be fixed to this plate so there will be 3/4 inch ali over the bearing carrier. Fingers crossed at this stage. I plan on fixing 40mm (I gave up on the conversion to inches on that one ) ali angle iron to the gantry sides as well.

    It would be better to have the gantry cross rail below the lower bearings and if needed I can do this as a major modification later.

    My lead screws are 1/2 inch single start 6TPI acme threads. This was the only acme thread I could get locally after days of enquiries. The 6 TPI doesn't convert to linear very well but it will do for starters. It has a double bearing at the motor and single on the other end and I have turned up my own version of AB nut. Half of it is sitting on the photo of the base unit but it is not tested yet so more later. I agree the Xylotex might be a bit light but it gets me started and at over $AUS600 shipped it was all I was willing to pay at this stage.

    It is expensive over here with low conversion rates and shipping costs. I got burnt for $AUS300 on ebay for a set of supposedly new Z axis linear rails so I am still recovering from that mistake. Description was new but no warranty and I blame myself for not being wiser. :frown:

    A feature I forgot to mention is that with this design the the bearing rails will be fully covered by the table so I should not be getting bumps from the bearings running over sawdust.

    I have a long way to go and appreciate any suggestions offered.

    Here is another photo of the base adjusting thingo.

    Attached Thumbnails Attached Thumbnails Gantry Router Log-base-detail-jpg  
    Last edited by Rodm1954; 12-04-2005 at 10:09 AM.
    cheers,
    Rod

    Perth, Western Australia


  8. #8
    Member ger21's Avatar
    Join Date
    Mar 2003
    Location
    Shelby Township
    Posts
    35538
    Downloads
    1
    Uploads
    0

    Default

    40mm = ~1-9/16"

    $600 for a Xylotex I'm using a Xylotex for cost reasons as well, even though I'd rather be using Gecko's.

    Don't worry about the 6tpi. Once you set up the software, it doesn't matter what the lead is. How long does it take to adjust all those bearings?

    Gerry

    UCCNC 2017 Screenset
    [URL]http://www.thecncwoodworker.com/2017.html[/URL]

    Mach3 2010 Screenset
    [URL]http://www.thecncwoodworker.com/2010.html[/URL]

    JointCAM - CNC Dovetails & Box Joints
    [URL]http://www.g-forcecnc.com/jointcam.html[/URL]

    (Note: The opinions expressed in this post are my own and are not necessarily those of CNCzone and its management)


  9. #9
    Registered
    Join Date
    Oct 2005
    Location
    Australia
    Posts
    612
    Downloads
    0
    Uploads
    0

    Default

    The bearings are very easy to adjust and have the added advantage of allowing me to square things up. I have tapped the bearing holders so it is simply a matter of holding the bearing against the rail and tightening the bolt.

    Before we converted to metric I was brought up on imperial measurement. My rules and tapes have both measurements and I work in both units. I visualise imperial for most things even though it has been forty years in metric for us.

    The conversion was strange because for a long time they still made imperial sizes and just nominated the nearest mertic equivalent.

    I just realised I have just highjacked my own thread.

    Thanks for the heads up on the 6TPI.

    cheers,
    Rod

    Perth, Western Australia


  10. #10
    Registered
    Join Date
    Oct 2005
    Location
    Australia
    Posts
    612
    Downloads
    0
    Uploads
    0

    Default

    Gerry
    I have taken up your advice on the support for the bottom bearings. What I have done is flip the ends so that I now have 2 inches clearance under the base. This will let me extend the gantry sides below the base and I can fix another cross piece between the gantry sides. This means one cross piece above the bearing carrier and one below.

    I have also had a look at using screws to push the bearing pivots to make adjusting easier. I will include this when I rebuild it this weekend. Last weekend I built the bench to mount it on and I will paint all the bits and re-assemble it on the new bench. I got my X axis rails and bearings yesterday and are very pleased with them. 20mm shaft and four slide bearings and mounting blocks. I have a complete Z axis assembly with ballscrew in transit. With these components once I build the gantry it should progress much quicker than I had anticipated. I will post some more pictures after this weekend.

    What I would like is some advice on a method to allign both rails during assembly. With all the adjustments I have incorporated I have the potential to make this machine very accurate but I can't think of a foolproof way to make both rails parallel and on the same plane. It would be very easy to build a machine with a twist in it.

    Any suggestions would be really appreciated?

    cheers,
    Rod

    Perth, Western Australia


  11. #11
    Registered
    Join Date
    Oct 2005
    Location
    Australia
    Posts
    612
    Downloads
    0
    Uploads
    0

    Default

    Progress is slow but moving forward. I built a bench to mount it on and have pulled it apart and painted the steel.

    I modified it by reversing the ends to lift the base off the table so I could attach a lower cross member. The gantry is finished and after a bit of adjustment it rolls very well. To make it perfect I need to adjust the rails slightly to make them parallel but I ran out of time tonight.

    We are now into our summer and it is becoming too hot for daytime work so it has started to become a bit of a chore. I am hoping I will spark up after I attach a motor and see some movement.

    A few pictures to update the thread.

    Attached Thumbnails Attached Thumbnails Gantry Router Log-first-assembly2-jpg   Gantry Router Log-railback2-jpg   Gantry Router Log-rail2-jpg   Gantry Router Log-raildetail2-jpg  

    cheers,
    Rod

    Perth, Western Australia


  12. #12
    Registered
    Join Date
    Oct 2005
    Location
    Australia
    Posts
    612
    Downloads
    0
    Uploads
    0

    Default

    I pulled the gantry apart again and bored a couple of holes to reduce the weight.

    I finished the adjusters for the bearing which has made it very easy to align and adjust the gantry. I am pleased with the gantry - smooth and no play or racking along the entire travel.

    AB nuts are now finished and seem to work well. I machined two flanges and welded the stock nuts inside the flange. Springs between the plates keep the set screws tensioned.

    Next step is to mount the acme thread and attach a motor for some movement.

    Attached Thumbnails Attached Thumbnails Gantry Router Log-gantry_3-jpg   Gantry Router Log-bearings_3-jpg   Gantry Router Log-ab_nut_3-jpg  
    cheers,
    Rod

    Perth, Western Australia


  13. #13
    Registered
    Join Date
    Oct 2005
    Location
    Australia
    Posts
    612
    Downloads
    0
    Uploads
    0

    Default

    I finished the framework for the cutting table. 50mm by 3mm ali angle in a sort of torson box design. MDF will cover the table and threaded inserts used for hold down clamps.

    Attached Thumbnails Attached Thumbnails Gantry Router Log-gantry-table_4-jpg  
    cheers,
    Rod

    Perth, Western Australia


  14. #14
    Registered
    Join Date
    Oct 2005
    Location
    Australia
    Posts
    612
    Downloads
    0
    Uploads
    0

    Default

    Still ticking along and learning heaps. I have very kindly been given acme thread and delrin nuts so a slight change of plans. I finished the table and will mount it next. I worked on the lathe and mill all day making the bearing mounts for the X axis and motor mounts. The shoulder on the bearing holder is to locate it in the frame to help allign the motor to the axis. Photos should show you how it goes together.
    Here are the results.

    Attached Thumbnails Attached Thumbnails Gantry Router Log-bearing-holder_5-jpg   Gantry Router Log-leadscrew_5-jpg   Gantry Router Log-leadscrew_installed_5-jpg   Gantry Router Log-motor-mount_5-jpg  

    Gantry Router Log-frame_5-jpg  
    cheers,
    Rod

    Perth, Western Australia


  15. #15
    Registered
    Join Date
    Oct 2005
    Location
    Australia
    Posts
    612
    Downloads
    0
    Uploads
    0

    Smile

    Hello

    Not much to show for a couple of days work but I have done the final adjustments on the X axis and leadscrew. Installed the table and fitted the Y axis rails.

    The table is good and the gantry is solid as a rock and rolls easily. I think having so many bearings around the rails has helped quite a bit.

    The 20 mm linear rails are good on the 700mm Y axis but I don't know how they would go over longer spans. I think on anything over this span I would go 25mm or linear rails with trucks.

    More photos and starting to look like a CNC gantry router now.

    Attached Thumbnails Attached Thumbnails Gantry Router Log-router_6-jpg   Gantry Router Log-router_front6-jpg   Gantry Router Log-router_side6-jpg  
    Last edited by Rodm1954; 01-14-2006 at 10:13 AM.
    cheers,
    Rod

    Perth, Western Australia


  16. #16
    Registered
    Join Date
    Oct 2005
    Location
    Australia
    Posts
    612
    Downloads
    0
    Uploads
    0

    Default Getting closer to finishing

    Finished fitting the Z axis tonight. The finished work area is :
    X - 760mm or ~30 inches
    Y - 550mm or ~21.5 inches
    Z - 150mm or ~6 inches (clearance between bottom of Z axis and table).

    Z will be reduced to 120mm or ~4.7 inches when the router is fitted.

    I still have to make and fit the Y axis leadscrew and the router plate. In two weeks it should be making a noise and if it works I will be making a louder noise.

    Attached Thumbnails Attached Thumbnails Gantry Router Log-z_7-jpg   Gantry Router Log-z_axis_7-jpg  
    cheers,
    Rod

    Perth, Western Australia


  17. #17
    Registered
    Join Date
    Oct 2005
    Location
    Australia
    Posts
    612
    Downloads
    0
    Uploads
    0

    Thumbs up Wahoooo - it's finished

    It is finally finished and is ready to go. The dirver board and wiring harness was done before I started making the machine so this weekend it should be making a noise. Well not a loud noise as I am going to use a spring loaded pencil to make patterns on paper until I iron out any bugs and learn to use the software.

    Last photos of the machine building is the Y axis leadscrew. Not much to show but it took three days to finish this bit. A lot of lathe work and milling.
    I won't bore you with details as the photos should show how I did it.

    I have really enjoyed making this and I think I am addicted to building these as I have parts ready for number two and three machines. These will be ballscrew and linear rails and I am looking forward to improving on this one.

    I hope that this thread provided some interest even though I think I might have broken the record for consequetive posts. It has been good to put something back to the forum that has given me the inspiration and courage to finally have a go.

    Attached Thumbnails Attached Thumbnails Gantry Router Log-y_lead_8-jpg   Gantry Router Log-y_lead_b_8-jpg   Gantry Router Log-router_8-jpg  
    cheers,
    Rod

    Perth, Western Australia


  18. #18
    Registered
    Join Date
    Jul 2003
    Location
    NE Ohio
    Posts
    167
    Downloads
    0
    Uploads
    0

    Default

    very nice. one of the cleanest I've seen. please post your results when you get it running.



  19. #19
    Moderator CNCRob's Avatar
    Join Date
    Feb 2005
    Location
    USA
    Posts
    921
    Downloads
    0
    Uploads
    0

    Default

    Your machine looks very nice! Keep us posted



  20. #20
    Registered
    Join Date
    Oct 2005
    Location
    Australia
    Posts
    612
    Downloads
    0
    Uploads
    0

    Default

    Thanks for the comments. I will post the results but it will be a few weeks because I have to learn CAD as well as TurboCNC.

    Does anyone have something interesting, either Gcode or Drawing that I can use to do some trials. I am going to use a spring loaded pencil until I work out how to use the software and iron out any bugs in the machine.

    cheers,
    Rod

    Perth, Western Australia


Page 1 of 3 123 LastLast

Tags for this Thread

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  


About CNCzone.com

    We are the largest and most active discussion forum for manufacturing industry. The site is 100% free to join and use, so join today!

Follow us on


Our Brands

Gantry Router Log

Gantry Router Log