PDA

View Full Version : How to verify material removal in more than one job?



kardang
04-28-2009, 05:19 AM
This might well be very obvious an deasy, but I cannot figure out how to verify two jobs in a row in SurfCam Verify V3. Say I want to run the roughing job, and remove a lot of material, then verify a finishing job. It looks like the fininshing job starts with the full stock, and that makes it difficult to see wether it moves correctly. Is there a way I can cintinue removing material based on the result of another job, in SurfCam verify,.

Cheers

Best regards
Jens Tandstad

Excelmachine
05-01-2009, 05:02 PM
During the verify operation, there is an Icon that says "save model". You can use this for what you are describing. Verify the rough operation and then save it using that button. Then when you want to verify the finishing operation, open the roughing model and use it from that stage. I hope this answers your question.

Leo

Yefim.C
05-28-2009, 03:01 PM
You can verify rough cut and safe file in VERIFY
Than for any other operations open saved file and verify next op.
or you can create STL files and load for Stock material