    I have a Okuma MX40HA, OSP7000 control.

    We are trying to give an M60 command, and nothing happens. I have confirmed ATC is on sequence #1, and APC is on Sequence #1. On the diagnostic screen, we get a 10968 APC A Position is not completed message. I have tried manually stepping the pallet changer in reverse and forward, nothing happens...

    Any help would be great!

    Thanks!


  2. #2
    Registered
    Join Date
    Dec 2008
    Location
    united states
    Posts
    18
    Downloads
    0
    Uploads
    0
    I have tried bringing the Z out and cleaned chips very thoroughly...
    I still cannot seem to make the Z axis A position switch...


  3. #3
    Flies Superman's Avatar
    Join Date
    Dec 2008
    Location
    Krypton
    Posts
    1772
    Downloads
    0
    Uploads
    0
    - Is the ATC toolchange in mid cycle ie. in any sequence other than #1 or #5 ? ( recheck )----spindle must also be clamped
    - Is the pallet comming in got 2 lights up ie W.LOAD FINISHED & set to the indexing position ?
    - Is your rapid override set to zero ? <---
    our MX used G30P3 & P4 for pallet positioning before doing a pallet change ie. Z goes home, ( then may move to an X&Y position ), then rotates to machine B-zero.

    Check this thread for am Xmas present, posted 3 years ago
    OKUMA MA40 HA variables


  4. #4
    Registered
    Join Date
    Dec 2008
    Location
    united states
    Posts
    18
    Downloads
    0
    Uploads
    0
    Yes, I have confirmed ATC is on sequence #1, I went ahead and did a full manual ATC sequence (Just in case). It is back to #1. Rapid override is set to 0. I gave the G30P4 command (Pallet change position). I have confirmed that I have both lights on (Pallet ready, etc.). Is there a mechanical switch that might be bad? I have removed the telescoping covers on each side of the tombstone. I saw the Z axis over travel dog switch, I have confirmed that it is working with my meter. I also noticed a pneumatic solenoid, but it looks like that is not needed till APC sequence #3. I am on #1 and cannot move to sequence #2.


  • #5
    Flies Superman's Avatar
    Join Date
    Dec 2008
    Location
    Krypton
    Posts
    1772
    Downloads
    0
    Uploads
    0
    - Is there any axes wanting to move after executing the M60. ie "Distance to go" ie B rotation ( try moving all axes , and then try the M60, to see movement )
    - the pallet ( in the machine ) must be able to move to the pallet change position or you will get a timeout alarm, increase the rapid rate override
    - pallet base must be present on the other fork before it will lift

    What solution info is given when you push the ? button ( near F1 key ) while the alarm is active ?

    - I'm not with the company to be of further help, sorry


  • #6
    Registered
    Join Date
    Apr 2009
    Location
    USA
    Posts
    495
    Downloads
    0
    Uploads
    0
    Superman is right, it will not change unless the home position is reached (as shown on your diagnostics page) Feedrate can not be at 0 to do this.

    Which type of indexing do you have? 1 degree or full B? If you have 1 degree the pallet will try to lift to rotate and sometimes an air pressure regulator under the table needs to be adjusted.

    Like Super says: are there any "Distance to go" shown?

    Best regards,


  • #7
    Registered
    Join Date
    Dec 2008
    Location
    united states
    Posts
    18
    Downloads
    0
    Uploads
    0
    I have tried moving the axes and giving the M60 command. Nothing moves...
    However, when I give G30P3 command, all axes move into position. I do have both pallets in the machine and have confirmed the pallet ready sensor is working. When I hit the ? during the alarm, it tells me that either one of the inputs are not on...

    My machine has a full B axis. I am thinking about manually changing the APC sequence from 1 to 2 in the machine parameters. Then try to manually sequence to sequence #3 and see what happens. I am also interested in trying to manually unclamp the pallet, then manually lift the pallet by using the manual buttons on the hydraulic solenoids...

    What do you think?


  • #8
    Registered
    Join Date
    Dec 2008
    Location
    united states
    Posts
    18
    Downloads
    0
    Uploads
    0
    Machine is running!

    I decided to change the parameter sequence to #2 (Knowing that my pallet was actually in the correct position). Then after that, the control let me continue on to step sequence #3 and so forth. After a full manual pallet change, it is now accepting the M60 command.

    Thanks!


  • Similar Threads

    1. Need Help!- Millac 4h pallet change program
      By fourway in forum Okuma
      Replies: 5
      Last Post: 03-04-2011, 06:46 AM
    2. HS1 pallet change speed
      By The CNC Noob in forum Haas Mills
      Replies: 0
      Last Post: 09-04-2009, 08:30 AM
    3. Pallet Change Speed
      By 68 SS in forum Fanuc
      Replies: 4
      Last Post: 09-19-2008, 10:36 AM
    4. Need Help!- HAAS HS-1 Pallet Change problems
      By cweiss in forum Haas Mills
      Replies: 3
      Last Post: 07-30-2008, 05:42 AM
    5. Pallet Change
      By CNC Mendez in forum G-Code Programing
      Replies: 6
      Last Post: 07-25-2006, 01:50 PM

    Posting Permissions



    About CNCzone.com

      We are the largest and most active discussion forum from DIY CNC Machines to the Cad/Cam software to run them. The site is 100% free to join and use, so join today!

    Follow us on

    Facebook Dribbble RSS Feed


    Search Engine Friendly URLs by vBSEO ©2011, Crawlability, Inc.