Originally Posted by
bytor
There are a whole host of questions that you need to answer before I could make a system recommendation.
What material are you cutting?
How thick is the material you will be cutting?
How much cutting are you going to be doing - 24/7? 4 hours a day? One small nest in an 8 hour shift?
What accuracy do you want - bolt fit? Bearing fit?
What is your nesting package?
Do you have a ready list of customers all set to use your service so your ROI is less than 5 years?
What is your definition of turn key?
I am sure you have thought this through and have a building that has sufficient electrical power available and you have the ability to plumb whatever gasses you need - even if it is just air - to the machine area.