Old 02-27-2009, 01:28 PM
 
Join Date: Nov 2007
Location: USA
Posts: 187
multiplex is on a distinguished road
1st machine rebuild

I built my first router back in october of 2007. It was built specifically to help out with a large production job i had at the time. Luckily i got the machine up and running with very few issues, but there were always some weaknesses in the design.

I've been running the machine weekly since that time, and finally have a break in my work which should allow me to fix some of the issues.

two things i'm going after.

1. Gantry rigidity. I largely underestimated the impact of cutting forces. The gantry was fabricated out of 3/4" pvc due to its price and its machinabilty. Poor choice for obvious other reasons.

2. Travel speed. I'm stuck at around 80ipm

Here are some pics of the current build. I will be keeping the base, which is very sturdy and welded up out of 2"x2" angle iron. Underneath are two VXB 25mm linear rails for Y axis









Plans are as follows..

One.

Keep the same machine layout and design concept. Replace / rebuild entire gantry out of extruded aluminum channel.

for the plate that connects the Y axis bearings under the table, i will use 2.8" x 10" x .5" aluminum channel.

On either end will be 1/2" or 3/4" 10" wide aluminum by about 18" tall.

From there i will mount a piece of 2.5" x 8" x .5" aluminum channel vertically where the X axis linear rails will mount.

I will also use some of the left over 10" wide aluminum to made the trolley for the router.

example of the channel



Two.

Switch out the X axis linear rails to 60" lengths to give me an X travel of 49" (verses 44" i have now)

Three.

Switch out my 1/2-10 2 start screws for 5 start to help improve my IPM's.


I just ordered the aluminum today, so hopefully things will be underway shortly i can post back up some progess.

Please let me know your thoughts / comments on this!

thanks
Tweet this Post!Share on Facebook
Reply With Quote

  #2   Ban this user!
Old 03-10-2009, 08:26 PM
 
Join Date: Nov 2007
Location: USA
Posts: 187
multiplex is on a distinguished road

just got in my aluminum channels today, so work is about to pick up.. started laying out the design and had two options to go with for the gantry. not sure how much of a difference there would be, but wanted to throw them out there for opinions

here is the current setup



layout 1 - just like old setup.



layout 2 - carriage straddles the x axis channel



shifts some of the weight behind the channel. based on the size of the channel being used, and the 3/4" aluminum that will connect it all - do either of these variations matter?

any input would be appreciated!
Tweet this Post!Share on Facebook
Reply With Quote

  #3   Ban this user!
Old 03-12-2009, 08:36 AM
 
Join Date: Nov 2007
Location: USA
Posts: 187
multiplex is on a distinguished road

anyone?? its lonely in here

for what its worth, i'm leaning towards version 2. started machining up a few parts last night that would work either way
Tweet this Post!Share on Facebook
Reply With Quote

  #4   Ban this user!
Old 03-12-2009, 05:43 PM
 
Join Date: Apr 2007
Location: USA
Posts: 5,441
CarveOne is on a distinguished road

I'm leaning toward #2 also. Go for it!

CarveOne
__________________
"A $1,000 electronic device will almost always protect a ten cent fuse."
Tweet this Post!Share on Facebook
Reply With Quote

  #5   Ban this user!
Old 03-12-2009, 09:18 PM
 
Join Date: Nov 2007
Location: USA
Posts: 187
multiplex is on a distinguished road

thanks!

did a little bit of work tonight. getting the support frame for the z axis going. The y axis linear bearings will bolt to this, along with the backlash nut.

waiting on a huge piece of 3/4" aluminum to arrive

notches are for linear rails and screw.. still needs mounting holes drilled for other items

Tweet this Post!Share on Facebook
Reply With Quote

Sponsored Links
  #6   Ban this user!
Old 03-12-2009, 09:21 PM
 
Join Date: Nov 2007
Location: USA
Posts: 187
multiplex is on a distinguished road

doublepost

Last edited by multiplex; 03-12-2009 at 09:24 PM. Reason: double post
Tweet this Post!Share on Facebook
Reply With Quote

  #7   Ban this user!
Old 03-13-2009, 12:58 AM
FandZ's Avatar  
Join Date: Oct 2008
Location: USA
Posts: 1,078
FandZ is on a distinguished road

I was going to say go with option 2 also but for somereason never got around to posting.

So how did you mill out that part? Did you use your old cnc machine?
Tweet this Post!Share on Facebook
Reply With Quote

  #8   Ban this user!
Old 03-13-2009, 07:48 AM
 
Join Date: Nov 2007
Location: USA
Posts: 187
multiplex is on a distinguished road

i used a standard bridgeport to machine these so far. for the larger spanning pieces, i'm going to make a drill jig to drill the ends - too long to setup on the machine.
Tweet this Post!Share on Facebook
Reply With Quote

  #9   Ban this user!
Old 03-16-2009, 09:57 PM
 
Join Date: Nov 2007
Location: USA
Posts: 187
multiplex is on a distinguished road

made some good progress tonight. my new 60" linear rails came in, along with all my stuff from dumpstercnc, and my big piece of 3/4" aluminum

router cart is complete minus a few small details. need to add in limit switches and whatnot.





with the 60" rails i should finally get my 48" travel. actually more like 49.5

Tweet this Post!Share on Facebook
Reply With Quote

  #10   Ban this user!
Old 03-16-2009, 10:20 PM
FandZ's Avatar  
Join Date: Oct 2008
Location: USA
Posts: 1,078
FandZ is on a distinguished road

Yep that looks solid. I know this is a noobish question, but how do you go about getting those vertical round rails in the front to stay in. How come they just don't fall out the other side? Are they tapered holes? I'm sorry for the lame question but I gotta know.
Tweet this Post!Share on Facebook
Reply With Quote

Sponsored Links
  #11   Ban this user!
Old 03-16-2009, 10:25 PM
 
Join Date: Nov 2007
Location: USA
Posts: 187
multiplex is on a distinguished road

totally valid question! well that is one aspect i did not complete yet. However i'm going to make a vertical slice in the top and bottom plate, and put a screw in perpendicular to the slice essentially making a clamp what will hold the rods in place

when using rods like this, its really important that the ends are clamped firm otherwise they can flex more than normal (i learned this on my first build, and later switched to supported rails)
Tweet this Post!Share on Facebook
Reply With Quote

  #12   Ban this user!
Old 03-16-2009, 10:36 PM
FandZ's Avatar  
Join Date: Oct 2008
Location: USA
Posts: 1,078
FandZ is on a distinguished road

Thanks for the explanation. Makes since. And I could see where clamping it would make a sturdier rail than just screwing the ends in. I'll keep checking back for updates.
Tweet this Post!Share on Facebook
Reply With Quote

Reply




Currently Active Users Viewing This Thread: 1 (0 members and 1 guests)
 
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is On
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
ES-L8 Spindle Rebuild big_mak Okuma 9 04-05-2009 02:12 PM
Rebuild of an very old Aciera F3 syyl Deckel, Maho, Aciera, Abene Mills 3 09-01-2008 02:17 AM
rebuild help houdini I.C. Engines 6 04-14-2008 09:16 AM
rebuild corrie CNC Wood Router Project Log 5 03-20-2008 05:29 PM
Haas Vf-2 Rebuild DEAN Haas Mills 7 09-18-2005 11:46 PM




All times are GMT -5. The time now is 11:48 PM.





Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2012, vBulletin Solutions, Inc.
Content Relevant URLs by vBSEO
Template-Modifications by TMS

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219 220 221 222 223 224 225 226 227 228 229 230 231 232 233 234 235 236 237 238 239 240 241 242 243 244 245 246 247 248 249 250 251 252 253 254 255 256 257 258 259 260 261 262 263 264 265 266 267 268 269 270 271 272 273 274 275 276 277 278 279 280 281 282 283 284 285 286 287 288 289 290 291 292 293 294 295 296 297 298 299 300 301 302 303 304 305 306 307 308 309 310 311 312 313 314 315 316 317 318 319 320 321 322 323 324 325 326 327 328 329 330 331 332 333 334 335 336 337 338 339 340 341 342 343 344 345 346 347 348 349 350 351 352 353