Thanks for the help guys. So far so good. I got my taps in this morning, set my z and gave it a shot. So far the parts are beautiful. But I've only run 3 (had to do a first artical through Q.A. before I start the run)
So really qurious to see how many parts I'll get on this tap. I'll let ya know.
Here's the program do you see any really stupid mistakes I should correct?
I've done alot of conversational CNC mill work over the last 10 yrs, not much G-code at all since college. So any advice, help or criticism is appreciated.
%
o0019(7716-01)
N1
T2 M06 (CEN-DRILL)
G00 G54 G90 X0.0 Y0.0
S2000 M03
G43 H02
G00 X-.620 Y-.1251
G00 Z.050
M08
G82 G98 Z-.050 R.05 F10.0
M09
N2
G00 G54 G90 T3 M6 (#35 DRILL)
G00 X-.620 Y-.1251 S1500 M03
G43 H03 Z.250 M08
G83 G98 Z-.550 R.050 F3.0 Q.035
M09
N3
G00 G54 G90 T4 M06 (M3X.5 ROLL TAP)
G00 X-.620 Y-.1251 S1000
G43 H04 Z.250
G84 G98 Z-.350 R.250 F19.68
N4
G00 G54 G90 T5 M06 (90* C-SINK)
G00 X-.620 Y-.1251 S1500 M03
G43 H05 Z.250 M08
G82 Z-.070 P.6 R0.1 F10.0
M09
M05
N5
T2 M6
M30
%
__________________ Poor planning on your part doesn't constitute an emergency on my part. |