Gibbsgod
Thanks for your input. . However if canned cycles were the problem it would be easy to solve. We have 40 machines with posts that were that simple. "Tool management", "Tool Monitoring" and "Part Measuring" A gantry loader that requires 12 lines of info when Gibbs outputs an "M" code just to call the subroutines is. "P" wait coding is a real pain as the lower turret must not be cutting whenever the upper mill head is tool changing or machine alarms out. The mill head has 2 separate magaines with 5 loading positions. 2 hours many many times over have been spent on this machine. I have been working with Charles Winston of Gibbs ( their post GURU ) for the past year on this. I think Gibbs needs to do their homework on MTM posts. For the money they charge and then ask me to debug it they should pay me. |